ISSN 1000-3665 CN 11-2202/P

    多孔小净距隧道合理施工时序的尖点突变分析方法与工程实践

    Analysis and practice of optimal construction sequence for multi-arch small-clearance tunnels based on the cusp catastrophe model

    • 摘要: 多孔隧道施工力学特性复杂,其方案选择及稳定性评价是工程难点,但是目前相关研究仍较少。以福建某浅埋偏压四孔小净距隧道为工程依托,构建三维力学模型分析了四种开挖时序下隧道变形规律;在此基础上,构建基于尖点突变理论的变形势能函数,综合考虑拱顶下沉、水平收敛等变形及发展态势,完成多孔隧道稳定性评价及施工方案优选,并结合工程实践验证方案合理性,提出稳定控制措施。力学分析表明,采用“先开挖埋深较小的右侧两洞、后开挖埋深较大的左侧两洞”方案时,隧道仰拱隆起、拱顶沉降及水平收敛分别为18.70,11.31,9.8 mm,比其他方案少10.09%~19.01%不等,远小于规定值且变形发展可控。基于尖点突变理论模型对不同时序下隧道整体稳定性评价结果表明,先开挖覆土厚度较小的右两洞、再开挖左两洞为较优进洞方案,计算结果拟合度总体大于0.95,预测准确度满足工程精度要求。变形计算及稳定性分析结果与现场监测、施工实际吻合性好,验证了计算方法、评价模型及施工方案的合理性。建议施工中应重点关注左车行隧道水平收敛变形情况,并根据需要对局部岩土体进行加固以减小洞口段偏压作用、降低拱脚拉裂风险。研究结果可为现场施工提供切实指导。

       

      Abstract: The mechanical characteristics of porous tunnel construction are complex, and the selection of its construction scheme and stability evaluation are engineering difficulties. This paper takes a shallow-buried, unsymmetrically-loaded four-hole small-clear-distance tunnel in Fujian as the engineering basis. A three-dimensional mechanical model is established to analyze the deformation laws of the tunnel under four excavation sequences. On this basis, a deformation potential energy function based on the cusp catastrophe theory is constructed. By comprehensively considering deformations such as vault settlement and horizontal convergence and their development trends, the stability evaluation of the porous tunnel and the optimization of the construction scheme are completed. Combined with engineering practice, the rationality of the scheme is verified, and stability control measures are proposed. Mechanical analysis shows that when the scheme of "first excavating the two right tunnels with smaller burial depth and then excavating the two left tunnels with larger burial depth" is adopted, the invert heave, vault settlement and horizontal convergence of the tunnel are 18.70, 11.31 and 9.8 mm respectively, which are 10.09%-19.01% less than those of other schemes, far less than the specified values and the deformation development is controllable. The evaluation results of the overall stability of the tunnel under different sequences based on the cusp catastrophe theory model show that the scheme of first excavating the two right tunnels with smaller overburden thickness and then excavating the two left tunnels is a relatively optimal tunneling scheme. The overall fitting degree of the calculation results is greater than 0.95, and the prediction accuracy meets the engineering precision requirements. The results of deformation calculation and stability analysis are in good agreement with on-site monitoring and actual construction, which verifies the rationality of the calculation method, evaluation model and construction scheme. It is suggested that during construction, focus should be placed on the horizontal convergence deformation of the left vehicle tunnel, and local geotechnical bodies should be reinforced as needed to reduce the unsymmetric loading effect at the tunnel portal section and the risk of arch foot cracking. The research results provide practical guidance for on-site construction.

       

    /

    返回文章
    返回